1. Describe the quiet hours as carefully as the peak
Rental enquiries often emphasise the largest motor or the busiest shift. The remaining hours can determine whether the selected set spends much of the hire lightly loaded. A site may need pumps and equipment during the day, then only lighting, controls or security services overnight. Record both periods before choosing capacity. An oversized running duty can remain hidden when an enquiry contains only the peak kVA.
Build a schedule showing simultaneous electrical demand in kW, duration, starting events and expected changes over the hire. Distinguish measured demand from estimated or nameplate figures. Identify critical loads that cannot be interrupted and any equipment that can be rescheduled. Ask how the schedule changes at weekends or between construction stages. The fleet dispatcher needs the operating picture, not simply the number printed on the proposed generator.
In a GOODWIND selection enquiry, send the low-demand duration alongside the most demanding start and identify which figures are measured or estimated. Ask the proposal to explain which requirement sets the capacity and how the selected engine’s instructions are addressed during the remaining hours. If a smaller unit is proposed, require the starting event, voltage recovery, site conditions and supply continuity to be reviewed again. Record the assumptions the dispatcher must verify before the equipment leaves the fleet.
Read the GOODWIND guide to generator loads, ratings and site conditions
2. Use the correct rating when describing low load
Identify the generator, engine, frequency and declared duty before calculating a percentage. GOODWIND’s current Cummins catalogue lists a 50 Hz GW-C110 configuration with a 6BT5.9-G2 engine at 80 kW/100 kVA prime and 88 kW/110 kVA standby. In a hypothetical site example, a 20 kW electrical load is 25% of that prime rating, but approximately 22.7% of the standby rating. These are arithmetic descriptions, not approved minimum operating limits.
The catalogue example helps explain the denominator; it does not provide a low-load duration allowance, a treatment programme or a fuel guarantee. Use the manual and applicable manufacturer guidance for the exact installed engine and generating-set configuration. Record the source revision with any proposed limit. Do not transfer a threshold from another engine family, a gas-generator article or a different emissions package.
Review the GOODWIND Cummins generator configurations
3. Understand the concern without diagnosing from appearance
Extended light-load operation can keep diesel combustion and exhaust conditions below those intended for a particular duty. Manufacturer guidance discusses incomplete combustion and deposits associated with prolonged low loading. Wet stacking describes the accumulation or discharge of unburned fuel, oil and related deposits in the exhaust system. It is an operating-condition concern that calls for model-specific review, not a diagnosis established by a photograph or a brief observation of smoke.
Caterpillar’s underloading guidance notes that visible exhaust slobber can also accompany low ambient or jacket-water temperatures. Its discussion also distinguishes engine concerns from exhaust-aftertreatment requirements. If the selected configuration has a DOC, DPF or SCR system, obtain the relevant temperature, regeneration and operating instructions. The presence and requirements of those systems must be confirmed for the actual unit; they cannot be inferred from the power rating.
Read Caterpillar’s technical discussion of generator underloading
Use these mechanisms to decide what information to collect, rather than copying another manufacturer’s numeric loading programme. Persistent leakage, unusual smoke, alarms or abnormal operation should be assessed by qualified personnel against the applicable instructions. Record when symptoms occur, what the load was and whether the cooling or exhaust system has been changed. Changing loading alone is not a substitute for diagnosing an equipment fault.
4. Make a low-demand dispatch review
| Review item | Evidence or decision to record |
|---|---|
| Running and starting demand | Measured or estimated kW schedule plus significant starting events. |
| Selected operating duty | Exact set, engine, frequency, rating and relevant manual revision. |
| Low-demand duration | Expected hours and sequence rather than one daily average. |
| Site continuity | Loads that can be interrupted and responsibilities for any changeover. |
| Monitoring and escalation | Who records load, alarms and symptoms, and who reviews deviations. |
| Any supplemental loading | Approved method, connection arrangement, responsible personnel and records. |
Compare the practical options against the same load schedule. For each proposed unit or combination, show the demanding start, the long low-demand period, the source-change sequence and any work the site must provide. A smaller unit may improve the running-load match but still needs the starting and continuity checks. Separate daytime and overnight duties, or reschedule noncritical work, only where the proposed arrangement meets the site requirements. Include transport, connections and supervision in the comparison; a lower nameplate rating does not establish the lowest delivered operating cost.
Where multiple sets and a suitable control system are being considered, ask whether the operating arrangement can reduce the number of lightly loaded machines. Paralleling, automatic start-stop and load sharing require compatible equipment, protection, defined operating logic and commissioning. Do not assume these functions are available because several generators can stand beside each other. A fleet proposal should identify the actual control package and who is responsible for system integration.
For an overnight unit, parallel arrangement or storage-assisted proposal, show the planned operating sequence and who changes the source. Check critical-load continuity, starting capability and the return to daytime duty. Include the extra transport, connections, supervision and maintenance in the comparison. Any projected saving should state its fuel and operating assumptions so the fleet can check them against the final equipment and hire schedule.
5. Treat a load bank as an engineered activity
A load bank can provide a controlled electrical load when the connected site demand is insufficient for a specified exercise or assessment. Cummins discusses supplemental resistive loading as one method used to address wet-stacking concerns. That general method does not determine the safe loading steps, duration, acceptance conditions or repetition interval for another machine. Those details need the selected equipment’s instructions and the responsible technical assessment.
Read Cummins service information on load-bank performance testing
Before dispatch, settle whether supplemental loading is required and who supplies, connects and operates the equipment. Confirm the electrical connection and isolation arrangements, cable and protection requirements, ventilation and hot-air discharge, access and site constraints. Identify how the connected loads and the load bank are considered together so the generating set is not overloaded. These are installation and operating responsibilities, not tasks to leave to an unbriefed hire customer.
Define what the activity is intended to show. A resistive load creates real-power demand, while a project may also require assessment of reactive loading, transient performance or other system behaviour. Record the selected test scope instead of treating one load-bank run as proof of every capability. Keep the loading sequence, actual kW, relevant temperatures, alarms and observations with the unit record. A successful session does not automatically erase an unresolved fault or authorise future operation outside the agreed duty.
6. Keep the return-to-base review connected to the next hire
At return, compare the recorded duty with the dispatch assumptions. Review hours at different loads, operating alarms, customer observations and any changes to the installation. Follow the applicable inspection and maintenance requirements, and escalate unresolved symptoms before the next dispatch. Do not substitute a universal oil-change interval or an arbitrary loaded-running period for the selected engine’s instructions.
Use repeated evidence to improve fleet allocation. If the same model repeatedly returns from a particular application with long light-load periods, review the enquiry process and dispatch choice. The useful question is whether the duty and the proposed solution were matched properly. A single average-load figure can hide several hours of very light operation followed by a short heavy period, so retain the time sequence where it affects the technical assessment.
Compare diesel generator configurations for your rental fleet
Agree who records load and alarms during the hire, who may change the configuration and which observations must be referred to the fleet owner. Give the customer the contact route and the information needed for that review, including the operating period, load and relevant alarms. Confirm the applicable warranty terms and service responsibilities in the hire and support documents. Keep those records consistent with the technical instructions rather than leaving the customer to decide whether a loading change or a service visit is required.
7. Questions rental buyers ask
Is 30% a universal minimum load for every diesel generator?
No. Published guidance often uses percentages within a stated manufacturer and duty context. The applicable limit, permitted duration and follow-up actions must come from the selected engine and generating-set instructions. Use a low-load percentage to flag a review, not as a universal pass-or-fail rule.
Can I solve the issue by choosing a smaller generator?
Ask for separate checks of the running load and the most demanding start, including any other loads already connected at that moment. Confirm the proposed unit’s response under the stated site conditions and its ability to carry the next stage of work. A smaller set is an option only after those requirements and the permitted supply interruptions have been reviewed.
Does a load-bank test guarantee trouble-free rental operation?
No. Ask for a record showing the test scope, load steps and duration, relevant conditions, alarms and unresolved observations. Use it to decide whether the unit is ready for the specified hire duty or needs further assessment. The report should distinguish a completed test from outstanding maintenance or fault investigation; neither is replaced by a general statement that the generator passed.
Prepare a rental-duty enquiry
Send GOODWIND the application, destination, frequency and voltage, the most demanding starting event and the kW expected in each operating period. Include low-demand duration, hire length, site conditions and permitted supply interruptions. Identify whether the proposal concerns one machine or a coordinated system, and any supplemental-loading arrangements. Ask the offer to state the capacity basis, configuration-specific operating information, site work and written responsibilities. Compare the proposed operating sequence as well as the equipment price before making a fleet purchase.
Use the GOODWIND checklist for comparing generator quotation scope
Discuss your rental-fleet load schedule and generator requirements with GOODWIND

